Overview
 
This function can be accessed from PO Entry > PO Line > Details button > Subcontract tab, OR can be accessed from the Site Map or Menu. This article reflects this function when accessing from the Site Map or Menu.

When the Subcontract Parent Item is added to a Purchase Order as a PO Line, the Subcontract Parent Item's BOM is extracted upon ‘Save’, creating PO Component Demand records (PODMD). This program allows you to review all of the PO Component Demands for a given PO Line and perform any necessary action or maintenance thereof from here.

Navigation

Subcontract PO Line Processing

Step 1 - With Division defaulting to the user's current Division, enter Purchase Order and Line Number, then hit 'Enter' to populate the page.

Header Fields

 

Division:  The Division under which the given PO is placed.

Purchase Order:  The Purchase Order Number associated with the given PO Line.

Line No:  The line number assigned by the system for the given Subcontract PO Line. 

Status:  The current status of the PO Line. 

Values are:

2 – Firmed
3 – Approvals Processing
4 – Approved
5 – Vendor Notified
7 – Line Item Partially Received
8 – Line Item Fully Received
9 – Close

 

Item:  The Item Number being purchased on this Purchase Order Line.

Qty Req:  The current total Quantity required on this PO Line.

 

Step 2 - Perform desired actions

New PO Components Demand Button

Click the button to bring up the PO Components page in Add mode.
 
Fields
 

Qty Req:  The current total Quantity required for the given PO Line.

Date Required:  This is the Date required for the given Subcontracted Component, calculated based on the defined lead time offsets.

Inv Division:  PO Component Inventory Division.

Enter Qty Per:  When checked, indicates that ‘Qty Per’ is the means that ‘Component Order Qty’ is/was calculated.

User-added image  EXAMPLE If ‘Qty Per’ is set to 2 and the PO Line is for 10 of the Parent item, then the Component Order Qty is calculated as 20.

Enter Component Qty
When checked, it indicates that the Quantity for the given component is to be entered directly as Component Quantity. In this case, the Qty Per will be calculated automatically.
 
Component Item Number:  This is the PO Component Item Number for the given subcontract component.

Backflush Policy Indicator:  The Backflush Policy for the given PO Component. It defaults from the Inventory Commodity Code and can be one of two choices: No Backflushing and PO Receipt. Components with the 'PO Receipt' option will be backflushed at the time of PO Receipt. ‘No Backflushing’ components can be issued using the PO Issue function. 

User-added image  NOTE Serialized items cannot be backflushed.

Inv Site:  PO Component Inventory Site from which inventory will be issued.

Issue From Inventory Location ID:  The Location ID from which inventory will be backflushed upon PO Receipt. Location ID must be a backflush location.

User-added image   NOTE  It must be a valid Location ID for the given Inv Site.

Qty Per:  When “Enter Qty Per” is checked, the quantity per field is enabled, and the value is entered here.

Component Qty: When either ‘Enter Component Qty’ or ‘Fixed Component Qty’ is selected, the quantity is entered in this field.
 
 

Allocate / Deallocate Buttons 

When allocations are active, click on the ‘Allocate’ button to allocate any available inventory or, conversely, click on the ‘Deallocate’ button to deallocate already-allocated components (that have not yet been picked).

 

User-added image  NOTE  Backflush items will be backflushed upon PO Receipt, even when not allocated. Non-backflush Items set to be allocated must be allocated before they can be issued using the PO Issue program. 

 

Grid Maintenance Button

Click the button to bring up the Grid Maintenance pop-up.

To add rows for new PO Components, click on the ‘Add’ button. 
Once data is entered in all fields, click on ‘Save’. 

User-added image  NOTE  There are columns to the right of what is visible in the pop-up that you need to use the scroll bar to access.

Fields

Component Item Number:  This is the PO Component Item Number for the given subcontract component.

Qty Per:  Enter Qty Per.

Qty Req:  The current total Quantity required for this component to support the quantity of the given PO Line (PO Line Qty X Qty Per). Note that this is a calculated field and cannot be entered directly.

 

Date Required:  This is the Date required for the given Subcontracted Component, calculated based on the defined lead time offsets. 

Inv Site:  PO Component Inventory Site from which inventory will be issued.

Issue From Inventory Location ID:  The Location ID from which inventory will be backflushed upon PO Receipt. Location ID must be a backflush location. 

 

User-added image   NOTE  It must be a valid Location ID for the given Inv Site.

Backflush Policy Indicator:  The Backflush Policy for the given PO Component. It defaults from the Inventory Commodity Code and can be one of two choices: No Backflushing and PO Receipt. Components with the PO Receipt option will be backflushed at the time of PO Receipt. ‘No Backflushing’ components can be issued using the PO Issue function. 


User-added image  NOTE Serialized items cannot be backflushed.

 

Extract Components button

 

This button extracts components for a Subcontract Purchase Order line when none are present. Upon selection, the system creates an SYDATA record of type Extract PO Components. When processed, the record retrieves the relevant BOM components, creates the corresponding PO Line Components, and displays them on the screen. 
For details, see the SYDATA - Extract PO Components.

 

User-added image  NOTE The PO line Status should be less than or equal to 5 (5 – Vendor Notified). 

 

Delete Components button

 

This button deletes all the PO Line Components from a Subcontract Purchase Order line where none of the PO Components are allocated or issued. Upon selection, the system creates an SYDATA record of type Delete PO Components. When processed, it deletes all the PO Line Components from the page. 
For details, see the SYDATA - Delete PO Components.

 

User-added image  NOTE  The PO line Status should be less than or equal to 5 (5 – Vendor Notified). 

 

SEE ALSO

Subcontract Purchase Order Processing
Subcontract Purchase Order Component Demand
PO Demand
SYDATA - Extract PO Components
SYDATA - Delete PO Components

Subcontract Purchase Order Component Issue
Subcontract Purchase Order Issue Reversal
Purchase Order Overview
Inventory Item Master
Division Master
Engineering Item Master

Settings
Subcontract PO Line Processing
Subcontract-PO-Line-Processing

Powered by