Overview
The Close Variance Tab presents the variances calculated by the software when the Work Order was Closed (Status-9).
Navigation
Work Order > Close Variance Tab
Close Var(Variance) Tab
Fields At Work Order Close (Status 9)
Final Var Material: This is the Final Variance amount for Material for this Work Order.
Final Var Labor: This is the Final Variance amount for Labor for this Work Order.
Final Var Material Ohd: This is the Final Variance amount for Material Overhead for this Work Order.
Final Var Labor Ohd: This is the Final Variance amount for Labor Overhead for this Work Order.
Final Var Fringe Ohd: This is the Final Variance amount for Overhead Fringe.
Final Var Freight: This is the Final Variance amount for Freight for this Work Order.
Final Var Other Landed: This is the Final Variance amount for Other Landed for this Work Order.
Final Var Machine Ohd: This is the Final Variance amount for Machine Overhead for this Work Order.
Final Var Subcontract Material: This is the Final Variance amount for Subcontracted Material for this Work Order.
Final Var Subcontract Labor: This is the Final Variance amount for Subcontracted Labor for this Work Order.
Final Var, Total: This is the Final Variance of Material, Labor, Material Overhead, Labor Overhead, Fringe Overhead, Machine Overhead, Subcontract Material, Subcontract Labor
IMPORTANT The Variance Account field on the Miscellaneous Tab is the Manufacturing Sub-Ledger Account to which the Work Order Variances will be charged. This field is sourced from the Item on the Work Order (Commodity Code or Item Override) and can be manually overridden on the Work Order.
SEE ALSO
Work Order Overview
Work Order Header Information
Work Order Statuses
Work Order Close